Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Surrey monitoring traffic as vehicles again clog city streets

Compared with city’s 2019 weekly average, deepest volume reduction was in late March with up to 46 per cent less vehicles

Surrey’s top cop is keynote speaker at Surrey Board of Trade AGM

Asssistant Commissioner Brian Edwards will be on deck at Tuesday’s ‘virtual’ meeting

Art’s Scarecrow Festival returns in September

Sixth annual event will be different than previous events because of the pandemic

‘Lifting Hands’ mural on White Rock wall celebrates community’s COVID efforts

High school students, grads inviting health-care workers, emergency crews to add handprints

Refund emails from City of White Rock a ‘phishing’ scam

IT staff work to nullify security breach in ‘classic phishing campaign’

B.C. records new COVID-19 death, 85 more cases; Horgan calls on celebrity help

This brings the total number of active confirmed cases to 531 across the province

Horvat scores 2 as Vancouver Canucks beat Blues 5-2 in NHL playoff opener

Game 2 in best-of-seven series goes Friday night

Teachers to get 2 extra days to prepare for students’ return, now set for Sept. 10

Students will first start with orientation and learn rules of COVID-19 classroom policies

High-volume littering at Cape Scott draws ire from hiking groups

Popular Vancouver Island hiking spot not closing, but frustration about crowding grows

SFU to drop ‘Clan’ varsity team name

The ‘Clan’ name is shortened from ‘Clansmen,’ and was introduced roughly 55 years ago

New Tory leader must build a strong team in Commons and for the campaign: Scheer

Scheer marked his final day in the House of Commons today as leader of the Opposition

B.C. to hire 500 more COVID-19 contact tracers ahead of fall

Contract tracers add an ‘extra layer’ in the fight against the novel coronavirus

Feds commit $305M in additional funds for Indigenous communities during COVID-19

Money can be used to battle food insecurity and support children and mental health

We were a bit tone deaf: Hobo Cannabis renamed Dutch Love after backlash

Hobo Cannabis has various locations in Vancouver, Kelowna and Ottawa

Most Read