Clayton Community Centre won’t open on schedule

A worker completes an air tightness test at the Clayton Community Centre. Because of a budget shortfall, the City won’t be opening the centre until 2021. (Photo courtesy of HCMA Architecture + Design)
Construction on the main foyer at the soon-to-be opened Clayton Community Centre. (Photo courtesy of HCMA Architecture + Design)
Artist’s rendering of the what the new Clayton Community Centre will look like from the outside. (Photo via surrey.ca)
A worker completes an air tightness test at the Clayton Community Centre. Because of a budget shortfall, the City won’t be opening the centre until 2021. (Photo courtesy of HCMA Architecture + Design) A worker completes an air tightness test at the soon-to-be opened Clayton Community Centre. (Photo courtesy of HCMA Architecture + Design)

The new Clayton Community Centre won’t be opening as planned this summer.

A report from the City of Surrey notes that a projected budget shortfall of between $37 to $42 million will prevent the City from opening a number of facilities, including the newly constructed community centre in Clayton.

“Staff are deferring the opening of Clayton Community Centre until the first quarter of 2021,” reads the report. “This facility will provide net new services to our residents and as such does not reduce current service levels. Furthermore, there is significant concern that given the COVID-19 pandemic there will be significantly reduced demand by the public for remainder of the year. In addition, staffing of the facility will result in hiring challenges given that some staff from other facilities are currently laid off.”

The report says delaying the opening of the more than $43 million facility by six to nine months – until the first quarter of 2021 – will save the City $2.5 million.

“We are aiming for June or July of this year!” a person from the City’s communications department wrote on Facebook in early March regarding when the new community centre was originally scheduled to open.

The report also notes that a number of civic facilities will remain closed, such as rinks, libraries, and other rec. centres.

None of this is setting well with Mike Bola, president of the Cloverdale Community Association (CCA).

Bola told the Cloverdale Reporter council needs to open the community centre on schedule.

“Why drag things out?” Bola asked. “Everything else is opening up as we enter phase two. Gyms are opening up. Why not the community centre?”

Bola said the CCA feels like Cloverdale’s being targeted.

“Why is it that they’re always going after small things? The ice rink was approved. We lost that. The money for that was already approved and it would have generated revenue. Now Clayton’s behind delayed. For what? To save $2.5 million on a $40 million facility?”

Bola said he’s frustrated rec. facilities aren’t opening while the SPD is still going ahead. He said if Mayor Doug McCallum thinks creating the SPD is important to tackle crime in the city, then he needs to understand that prevention and early intervention are just as important efforts towards marking the city safer.

“Keeping kids off the streets and giving them opportunities to stay active is important too,” Bola added. “I think mayor and council should delay the SPD. It’s not important enough right now. We have a police force. Make up the $42 million [current budget shortfall] and then continue on with the SPD after.”

PASSIVE HOUSE

The Clayton facility was built as a Passive House. Originating in Germany, Passive House is a unique way to construct a building that uses “super insulation” combined with a complex ventilation system to drastically reduce a building’s energy consumption.

Fresh air is continuously sucked into a building and stale air is continuously forced out. While the stale air is being forced out, it is used to heat the incoming air, which minimizes heat loss.

According to Passive House Canada, the low-energy buildings “consume up to 90 per cent less heating and cooling energy than conventional buildings.” This design includes being able to build houses without furnaces in cold climates.

The building was projected to cost $43.5 million — with Natural Resources Canada kicking in $1.3 million, the Federation of Canadian Municipalities Green Municipal Fund gifting $175,000, and BC Hydro donating $30,000.

The first Passive House in Canada was constructed in Whistler for the 2010 Winter Olympics. Lost Lake PassivHaus was built to showcase the unique construction methods to the building community.

The Clayton Community Centre is located at 7155 187A Street in Cloverdale.



editor@cloverdalereporter.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

COVID-19: Daily update on the pandemic in Surrey, White Rock and beyond

JULY 11: B.C.’s COVID-19 job recovery led by tourism, finance

Suspect in North Delta home invasion facing attempt murder charge

Blaine Robert Jackson, 37, of no fixed address, faces six charges in relation to this incident

‘Did anything good come out of my son’s overdose death?’ – South Surrey mom

Maggie Plett says action still needed on recovery homes

Rooftop hatchlings ‘a nice addition’ to White Rock RCMP operations

Pair of seagull chicks hatched in ‘fenced playground’ on July 2

PHOTOS: Surrey rally supports Mona Wang, calls for wellness check reform

Security camera footage shows Wang being dragged, stepped on during RCMP wellness check at UBCO

B.C. sees 25 new COVID-19 cases, community exposure tracked

One death, outbreaks remain in two long-term care facilities

B.C. Ferries increasing passenger capacity after COVID-19 restrictions

Transport Canada 50-per-cent limit being phased out, no current plans to provide masks

Once-in-a-lifetime comet photographed soaring over Abbotsford

Photographer Randy Small captures Comet NEOWISE in early-morning sky

BREAKING: Amber Alert for two Quebec girls cancelled after bodies found

Romy Carpentier, 6, Norah Carpentier, 11, and their father, Martin Carpentier, missing since Wednesday

Bringing support to Indigenous students and communities, while fulfilling a dream

Mitacs is a nonprofit organization that operates research and training programs

B.C. man prepares to be first to receive double-hand transplant in Canada

After the surgery, transplant patients face a long recovery

Grocers appear before MPs to explain decision to cut pandemic pay

Executives from three of Canada’s largest grocery chains have defended their decision to end temporary wage increases

Man shot dead in east Abbotsford suburbs

Integrated Homicide Investigative Team called to investigate

RCMP ‘disappointed’ by talk that race a factor in quiet Rideau Hall arrest

Corey Hurren, who is from Manitoba, is facing 22 charges

Most Read